How to turn the chosen approach reference into a durable, resumable plan file, and how to keep that file correct across the whole upgrade lifecycle: create it (Phase 4), maintain it during execution (Phases 5-8), and reconcile it on resume (Phase 0). These sections are what survives context compaction and what Phase 0 resumes from.
The plan is the durable, resumable source of truth: Phase 0 resumes from it,
and it is what survives context compaction. Any step that exists only as prose
in a approach reference — not as a discrete, tracked item in this plan — WILL
be skipped after compaction. A parse-clean signal (has_import_errors: false)
does NOT satisfy the test-run checkpoint and must never be recorded in a way
that reads as “validated” or “complete”. Generate these sections BEFORE
presenting the plan for confirmation; do not defer their creation to execution
time.
Compaction-survival rule for skill delegations: When a step requires
invoking another skill (e.g., testing-mwaa-workflow, debugging-mwaa-workflow,
authoring-mwaa-workflow), the text you write for that step MUST include the
word “skill” and name that skill explicitly. After compaction, the original
approach reference text is gone — the plan file is the only artifact the agent
reads on re-entry. A step that says “Test-run checkpoint [PENDING]” will be
ad-hoc’d with manual REST API calls; a step that says “invoke skill
testing-mwaa-workflow (delegated mode) and not manual DAG run triggers
[PENDING]” will trigger the correct skill invocation. This applies to every
step that delegates to a skill, not just the test-run checkpoint.
Open the chosen approach reference now and enumerate (a) every numbered step,
(b) every step marked REQUIRED or flagged as a checkpoint, and (c) every ##
record-section it names. Write each into the plan as a discrete PENDING,
trackable item. At minimum the generated plan MUST contain:
A ## Checklist section mirroring the chosen reference’s numbered steps
plus Phase 8, each with a status field. Flag every action that needs
confirmation (deploy to your current environment, create-environment, each
version jump, switchover, decommission) and every step labeled REQUIRED.
Multi-action steps must be decomposed — see the approach-specific
sub-step rules below.
Every required checkpoint from the reference as its own PENDING entry. By approach: New-environment upgrade — Step 4-checkpoint (test-run the new environment); Rehearsed in-place upgrade — Step 1-checkpoint (test-run the test copy; a hard prerequisite for the live upgrade), Step 3 re-check your current environment (REQUIRED); Direct in-place upgrade — Step 1 extra confirmation checkpoint, Step 4 test-run your current environment.
A pre-seeded ## Test-run results section, with one row per deployed DAG in
state PENDING (columns: DAG ID, run_id, State, Duration, Notes) and a
header stating it is REQUIRED and must be all-SUCCESS or NEEDS-DECISION
before switchover (New-environment upgrade) / before the live upgrade
(Rehearsed in-place upgrade) / before marking complete (Direct in-place
upgrade).
The test-run checkpoint step in the Checklist MUST use this exact wording pattern (the location named varies by approach):
Test-run checkpoint: run DAGs on the new environment — invoke skill testing-mwaa-workflow (delegated mode) and not manual DAG run triggers [PENDING, REQUIRED CHECKPOINT]Test-run checkpoint: run DAGs on the test copy — invoke skill testing-mwaa-workflow (delegated mode) and not manual DAG run triggers [PENDING, REQUIRED CHECKPOINT]Test-run checkpoint: run DAGs on your current environment — invoke skill testing-mwaa-workflow (delegated mode) and not manual DAG run triggers [PENDING, REQUIRED CHECKPOINT]The word “skill” and the “not manual DAG run triggers” clause are not decorative — they are the re-entry instruction that survives compaction. Without them, a resuming agent will ad-hoc trigger-and-poll via the REST API instead of invoking the structured testing skill.
For the New-environment upgrade, a ## Switchover progress table
pre-seeded with one row per batch and columns: Batch, Current environment
paused, New environment unpaused, Monitored one full cycle?, Advanced. The
plan must not advance a batch until its Monitored one full cycle? cell is
yes. The Rehearsed in-place upgrade has no switchover — omit this table
for it; use the batch table’s per-DAG status for test-copy deployment
tracking instead.
A ## Where we are block: working_on, current_jump, jump_status,
phase (which of the skill’s Phases 0–8 the upgrade is in),
test_run_checkpoint (NOT-PASSED / PASSED). For the Rehearsed
in-place upgrade, add live_upgrade_allowed — yes / no (yes only
after the test-run checkpoint is PASSED) so a resuming agent cannot start
the irreversible live upgrade on parse-only evidence.
Phase 8 broken into discrete tracked items: 8.1: Batched switchover [PENDING] (New-environment upgrade only), 8.2: Stability period [PENDING], 8.3: Decommission [PENDING, NEEDS CONFIRMATION]. Do not track
Phase 8 as a single line.
The batch table’s status vocabulary MUST distinguish parse-clean from
test-run-verified. Use LOADED (uploaded, parses, zero import errors) as
distinct from VERIFIED; LOADED is never a completion state. For
multi-jump New-environment upgrade paths, add a Deploy Phase column
(A: original or B: fixed) to distinguish starting-version original DAGs
from post-target AF3-fixed DAGs — deploying Phase B code before the target
version jump completes causes ModuleNotFoundError.
Many numbered steps are multi-action procedures. If context compacts mid-step, the plan must record which sub-actions completed. The Checklist MUST decompose these steps into individually-tracked sub-items:
New-environment upgrade:
1a: create-environment +
1b: poll AVAILABLE. Do not proceed to Step 2 until status = AVAILABLE.Variables: [PENDING/SKIP/DONE], Connections: [PENDING/SKIP/DONE], Pools: [PENDING/SKIP/DONE]. Pre-populate SKIP for categories handled by a secrets
backend (detected in Phase 3 Step 4).4A: Deploy original DAGs (starting-version validation) and 4B: Deploy fixed DAGs (post-target). The batch table must record which deployment phase each DAG
is in. AF3-only imports (from airflow.sdk) MUST NOT be deployed until the
target version jump completes.Rehearsed in-place upgrade:
Direct in-place upgrade: no additional decomposition required beyond the existing Phase 4 mandate (Steps 1 and 4 are already individually tracked).
When any version jump crosses into a new major version, Phase 5 (Fix Code)
must be written into the plan as individually-tracked sub-items in the
Checklist. The re-scan step is the critical one — --unsafe-fixes can
introduce runtime-breaking patterns (notably _TaskDecorator.output) that
are invisible to Ruff but cause AttributeError at parse time on the target
version. If context compacts before the re-scan runs, the plan must still
instruct the agent to perform it.
Write Phase 5 into the plan as:
- [ ] Phase 5: Fix Code (cross-major) [PENDING]
- 5.0: Redesign metadata-DB-access DAGs (if any flagged in Phase 3):
ORM-access DAGs to REST API; CLI-access DAGs to MWAA CLI endpoint
(run `cheat-sheet` on target env to confirm command availability) [PENDING]
- 5.1-N: Fix batch 1..N DAGs (Ruff --fix --unsafe-fixes + manual) [PENDING per batch]
- 5.FINAL: Re-scan ALL fixed files for .output on @task refs + airflow db CLI
(sections 15/16). MUST run AFTER all --unsafe-fixes and manual edits are
complete. Grep patterns: `\.output` adjacent to @task-decorated function
names, `airflow db` or `airflow CLI` in BashOperator strings. Any hits
require a fix-and-re-verify cycle before proceeding to Phase 6/7. [PENDING]The 5.FINAL step is a required checkpoint: do not proceed to deployment
(Phase 7/8) until the re-scan is recorded as DONE with zero hits. Its
ordering constraint (“AFTER all --unsafe-fixes”) must appear in the plan
text — without it, a resuming agent may run the re-scan before applying
fixes, get a clean result, and then introduce the very patterns the re-scan
was meant to catch.
The plan is parsed by the agent itself on resume, so its structure must be predictable. Every plan MUST follow this contract.
PENDING, DONE, SKIP,
DROPPED, LOADED (uploaded + parses; not yet test-run), VERIFIED (test run
passed), NEEDS-DECISION (blocked on an external/infra dependency or a user
call), and for checkpoints PASSED / NOT-PASSED. Do not invent other status
words (no “in progress”, “partial”, “done-ish”).Last updated line: the first line after the plan title MUST be
Last updated: <UTC ISO-8601 timestamp> - <one-line what-changed>, rewritten
each time progress is saved. It is the freshness signal a resuming agent
reads first.## Where we are keys (fixed): working_on, current_jump, jump_status,
phase (which of the skill’s Phases 0–8 the upgrade is in),
test_run_checkpoint (PASSED / NOT-PASSED), and for the Rehearsed
in-place upgrade live_upgrade_allowed — yes / no (yes only after the
test-run checkpoint is PASSED).After completing any tracked item - a step, sub-step, version jump, checkpoint, batch, or per-DAG status - and BEFORE issuing the next action or command, save that change to the plan file. Never batch plan updates. Saving progress means updating three things together:
Last updated line and the ## Where we are block.Recording durable facts (not only status flips) is what prevents detail - not just progress - from being lost when context compacts. “Before the next action” is what keeps multi-action steps (e.g. the rehearsal’s create/migrate/version-jump/deploy sub-steps) from drifting behind reality.
Never write secret values into the plan. The plan is a durable on-disk
artifact. Record connection/variable migration as status tokens only
(PENDING/SKIP/DONE); never store passwords, connection strings, variable
values, or connection extra contents in it. Reference secrets by key/name only.
These invariants MUST always hold. A violation means the plan is mid-drift and Plan Reconciliation (below) must run before any further action. They are written against the plan’s roles so they hold for every approach; the “test-run checkpoint” is whichever checkpoint the chosen approach defines - the New-environment upgrade’s Step 4-checkpoint, the Rehearsed in-place upgrade’s Step 1-checkpoint, or the Direct in-place upgrade’s Step 4.
| # | Invariant | Applies to |
|---|---|---|
| 1 | A checkpoint marked PASSED requires all its prerequisite ## Checklist items to be DONE or SKIP. | New-environment upgrade, Rehearsed in-place upgrade, Direct in-place upgrade |
| 2 | ## Where we are.test_run_checkpoint equals the aggregate of the ## Test-run results table - any PENDING row means NOT-PASSED. | New-environment upgrade, Rehearsed in-place upgrade, Direct in-place upgrade |
| 3 | Every DAG the batch table shows deployed has a row in the ## Test-run results table. | New-environment upgrade, Rehearsed in-place upgrade, Direct in-place upgrade |
| 4 | current_jump / jump_status match the Upgrade Path table’s per-jump Status (for the Rehearsed in-place upgrade, whichever of the test-copy/current-environment columns applies to where you are). | New-environment upgrade, Rehearsed in-place upgrade, Direct in-place upgrade |
| 5 | No switchover batch is Advanced unless its Monitored one full cycle? cell is yes. | New-environment upgrade |
| 6 | live_upgrade_allowed is present and is yes only when test_run_checkpoint is PASSED (otherwise no). | Rehearsed in-place upgrade |
At session start and after any compaction, re-read the entire plan file before taking any action; never act on a remembered or summarized version. Then, before resuming work, run this reconciliation:
## Where we are.aws mwaa get-environment --name <env> - does the env exist, at what
version/status?aws mwaa invoke-rest-api --name <env> --method GET --path /dags
(paginate: loop offset by 100 until total_entries, per
discovery-preflight.md Step 1.4) - are the DAGs deployed, and is
has_import_errors false?aws mwaa invoke-rest-api --name <env> --method GET --path /health -
metadatabase/scheduler healthy, heartbeat advancing?Last updated
line.A stale PASSED test-run checkpoint invites a different destructive next
action per approach; reconciliation guards each:
| Approach | Stale checkpoint would trigger next | Danger |
|---|---|---|
| New-environment upgrade | switchover batch + delete-environment on your current environment | destroys the live fallback |
| Rehearsed in-place upgrade | irreversible live upgrade on your current environment | upgrades your current environment on false evidence |
| Direct in-place upgrade | mark migration complete | declares success unvalidated |